ContID 264509 EST NO 0001 |
Date:10/07/2026 |
COMMONWEALTH OF KENTUCKY
TRANSPORTATION CABINET
| Contract ID | 264509 | Estimate Number | 0001 | Estimate Type | DRAFT_PROGRESS | ||
| District Office | MADISONVILLE (02300) Brown, Timothy Blake | ||||||
| Contractor | N W K CONSTRUCTION INC | MARS ADDR SN 0 | |||||
| PO BOX 486 | |||||||
| HARRODSBURG , KY , 40330 | |||||||
| Pay Period | 06/26/2026 TO 10/01/2026 | ||||||
| Date Approved | 10/06/2026 | ||||||
| Primary Proj Number | 0208900812602 | ||||||
| Project No. | HSIP 5055(018) | ||||||
| Primary County | MUHLENBERG | ||||||
| Name of Road | KY HIGHWAY 81 (KY 81) | ||||||
| Description | FROM THE INTERSECTION OF US 431 EXTENDING NORTHWEST TO 0.035 MILES NORTH OF THE INTERSECTION OF CONWAY ROAD | ||||||
| Date Let | 04/23/2026 | Formal Acceptance | |||||
| Date Awarded | 05/05/2026 | Date Work Began | |||||
| Date Contract Executed | 06/26/2026 | Open To Traffic | |||||
| Date NTP Issued | 06/26/2026 | Actual Completion Date | |||||
| Current Contract Amount | $405,414.74 |
Total to Date |
Prev to Date |
This Estimate |
||
| Original Amount | $405,414.74 |
Total Earnings | $267,843.42 |
$0.00 |
$267,843.42 |
|
| Percent Complete | 66.07 |
Stockpiled Materials | $0.00 |
$0.00 |
$0.00 |
|
| Funds Available | $137,571.32 |
Gross Earnings | $267,843.42 |
$0.00 |
$0.00 |
|
| Total Change Orders | $0.00 |
Other Adjustments | $0.00 |
$0.00 |
$0.00 |
|
| TOTAL | $267,843.42 |
$0.00 |
267,843.42 |
|||
| Contract Id | 264509 | Change Order Summary |
County | MUHLENBERG | ||||||
| Estimate Nbr | 0001 | Project Number | HSIP 5055(018) | |||||||
| Contractor | N W K CONSTRUCTION INC | Period | 06/26/2026 TO 10/01/2026 | |||||||
| CHANGE ORDERS HISTORY | ||||||||||
| CHANGE ORDER NBR | DESCRIPTION | STATUS | APPROVAL DATE | TOTAL CO AMOUNT | CONTRACT TIME ADJUSTED | |||||
| 001 | Liquidated Damage OVERRIDE | Approved | 09/17/2026 | $0.00 | 0.0 | |||||
| 002 | Bridge Case 1 | Pending | 0 | $2,750.00 | 4.0 | |||||
CONTRACT ADJUSTMENTS HISTORY
| Contract Adjustments |
|
|
| Adjustment Description | Est No |
Adjustment Amount |
| Line Item Adjustments History | |||||||||
| PROJECT | ITEM NBR | DESCRPITION | TYPE | EST NO | ADJ QUANTITY |
UNIT PRICE |
ADJUSTED AMOUNT |
||
| Contract Id | 264509 | COMMONWEALTH OF KENTUCKY |
County | MUHLENBERG | ||||||
| Contract Type | GUAR GUARDRAIL | TRANSPORTATION CABINET |
Primary Project Number | 0208900812602 | ||||||
| Estimate Nbr | 0001 | Period | 06/26/2026 TO 10/01/2026 | |||||||
| Contractor | N W K CONSTRUCTION INC | |||||||||
| Project | 0208900812602 | Fed/State Project Number | HSIP 5055(018) | Category | ||||||||
| LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
| Project | 0208900812602 | Fed/State Project Number | HSIP 5055(018) | Category | 0001 ROADWAY | |||||||
| 0005 | DGA BASE | 00001 | TON | 46.00 | 46.000 | 0.000 | 0.000 | 81.74 | 0.00 | |||
| 0010 | ASPHALT SEAL AGGREGATE | 00100 | TON | 3.34 | 3.340 | 0.000 | 0.000 | 601.87 | 0.00 | |||
| 0015 | ASPHALT SEAL COAT | 00103 | TON | 0.40 | 0.400 | 0.000 | 0.000 | 7,500.00 | 0.00 | |||
| 0020 | DELINEATOR FOR G/R BI DIRECTIONAL WHITE | 01987 | EACH | 126.00 | 126.000 | 100.000 | 0.000 | 100.000 | 12.00 | 1,200.00 | 1,200.00 | |
| 0025 | G/R-W BEAM-S FACE TL-3 | 02351 | LF | 8,545.00 | 8,545.000 | 7,643.750 | 0.000 | 7,643.750 | 30.84 | 235,733.25 | 235,733.25 | |
| 0030 | G/R TERMINAL SECTION NO 1 | 02360 | EACH | 4.00 | 4.000 | 0.000 | 0.000 | 71.00 | 0.00 | |||
| 0035 | G/R END TREATMENT TYPE 1 | 02367 | EACH | 10.00 | 10.000 | 3.000 | 0.000 | 3.000 | 4,525.00 | 13,575.00 | 13,575.00 | |
| 0040 | REMOVE G/R | 02381 | LF | 8,893.00 | 8,893.000 | 8,725.000 | 0.000 | 8,725.000 | 3.45 | 30,101.25 | 30,101.25 | |
| 0045 | MAINTAIN & CONTROL TRAFFIC MUHLENBERG KY 81 HSIP | 02650 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 16,000.00 | 0.00 | |||
| 0050 | PORTABLE CHANGEABLE MESSAGE SIGN | 02671 | EACH | 2.00 | 2.000 | 0.000 | 0.000 | 250.00 | 0.00 | |||
| 0055 | STAKING MUHLENBERG KY 81 HSIP | 02726 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 500.00 | 0.00 | |||
| 0060 | OBJECT MARKER TY 3 | 20191ED | EACH | 10.00 | 10.000 | 4.000 | 0.000 | 4.000 | 20.98 | 83.92 | 83.92 | |
| 0065 | RAIL SYSTEM SIDE MOUNTED MGS | 25017ED | LF | 90.00 | 90.000 | 0.000 | 0.000 | 242.00 | 0.00 | |||
| 0070 | THRIE BEAM G/R TRANSITION TL-3 | 25078ED | EACH | 4.00 | 4.000 | 4.000 | 0.000 | 4.000 | 2,600.00 | 10,400.00 | 10,400.00 | |
| 8000 | LIQUIDATED DAMAGES Contract Overtime | 10111NS | DOLL | 0.00 | 0.001 | -23,250.000 | 0.000 | -23,250.000 | 1.00 | -23,250.00 | -23,250.00 | |
| 8002 | G/R-BRIDGE CASE I | 08805 | LF | 0.00 | 0.000 | 0.000 | 0.000 | 110.00 | 0.00 | |||
| Project | 0208900812602 | Fed/State Project Number | HSIP 5055(018) | Category | 0002 DEMOBILIZATION | |||||||
| 0075 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 6,000.00 | 0.00 | |||
| SUBTOT | $267,843.42 |
$267,843.420 |
||||||||||
| LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
| SUBTOT | 0.00 |
$0.000 |
||||||||||